The Foundation is in for the Amherst NH Garage Project!
The foundation forms have been set for the garage addition in Amherst NH and are ready to be removed. The Town of Amherst Building Inspector will be by the jobsite on Monday morning to check that we meet the correct NH Building Codes. We had Kenny Rocca of Wilton NH using his excavator to dig the hole and JC Foundations, Jeff Creighton, out of Greenville NH set the forms. Once the foundation passes inspection Kenny will be back to backfill the foundation and the guys can start their framing for this addition, which will have a family room above for future use. This project should take us approximately 6 weeks to completely build, insulate, drywall, roof, install siding and install windows.